BAYSHORE
NEIGHBORHOOD - BID PACKAGE NO. 8A |
|
|
•
Description
•
Funding
•
Implementation
Schedule |
•Basis
of Design Report
•Community
Workshop |
| |
DESCRIPTION
|
Bid Package 8A: Central
Bayshore Improvements Project Description:
Bid Package 8A: Central
Bayshore Improvements Project Description:
The Central
Bayshore sub-neighborhood is generally described
as that area bounded by 41st Street to
the north, Dade Boulevard to the South, Pinetree
Drive to the East, and Alton Road to the West. The
area consists of single-family residences, with
pockets of low-density multi-family structures. It
is important to note County and State Roadways are
not included within the scope of the City’s Row
improvements Program. Hence, 41st
Street, Pine Tree Drive, Alton Road and Dade
Boulevard are excluded from the scope of this
Project. The Central Bayshore Right-of-Way
Improvement project will include a variety of
streetscape, water and Stormwater upgrades.
The design of this Project is near completion but
requires new Bond issue in FY 2009 to commence
construction.
For
additional details, please click on the Drawings
Link to the left. |
|
|
 |
|
| The
Bayshore Neighborhood. Click photo to enlarge. |
| |
Return
to top of page
FUNDING
The total
construction and contingency budgets for the various
sub-neighborhoods are as follows
|
|
BID PACKAGE 8A CENTRAL BAYSHORE FUNDING
- (March 2009) |
|
General
Obligation Bonds and Unfunded |
Water & Sewer
Bonds –Incl Gulfbreeze |
Stormwater Bonds |
Future Water /
Sewer Bonds |
Future
Stormwater Bonds |
|
$4,175,516 |
$823,017 |
$1,472,444 |
$10,467,000 |
$13,633,489 |
|
Total Proposed
Funding |
$30,571,466 |
|
|
Return to top of page
IMPLEMENTATION
SCHEDULE
|
BID PACKAGE 8A CENTRAL BAYSHORE -
Implementation Schedule as of
March 2009 |
|
Planning |
21 Months |
July 2001 -
April 2003 |
|
Negotiations for
Design / Bid / Award / CM extended to November
2003 |
|
Design &
Permitting |
74 Months |
December 2003 –
January 2009 |
|
Bid / Award |
5 Months |
October 2009 –
February 2010 |
|
Construction |
24 Months |
March 2010 –
February 2012 |
|
SYNOPSIS:
Design completed. Pending
new Bond Funding to move into construction. |
Return
to top of page