FLAMINGO/LUMMUS NEIGHBORHOOD - BID PACKAGE NO. 10D
PROJECT COMPLETED
 
 
Description
Funding
Implementation Schedule
 

DESCRIPTION

On July 3, 2006 the City held a Grand Re-Opening Celebration commemorating the "Ave-New". Attended by a significant number of business owners and community leaders - the project was hailed as a success by all. Remaining work in the Lummus area is a part of the Bid Package 10B Lummus Streetscape Project.

This Project is completed.

For additional details, please click on the Photos Link to the left.

 


The Flamingo/Lummus Neighborhood.
Click photo to enlarge.



 


FUNDING
The total construction and contingency budgets for the various sub-neighborhoods are as follows:
 

BID PACKAGE 10D WASHINGTON AVENUE FUNDING

Project Completed March 2007

Water & Sewer Bonds

$2,013,910

Stormwater Bonds

$5,396,431

City Center RDA

$3,534,566

South Pointe RDA

$1,981,468

General Fund

$1,595,148

Resort Tax

$284,877

Transit Tax

$1,611,555

Parking Enterprise Fund

$179,985

 Total Funding

$16,597,940

 


Return to top of page

IMPLEMENTATION SCHEDULE

BID PACKAGE 1OD WASHINGTON AVENUE DESIGN /BUILD – Implementation Schedule

Bid / Award

12 months

April 2003 - March 2004
Construction

25 months

April 2004 – August 2006
Amendments to the Original Contract

18 months

May 2006 – April 2008


SYNOPSIS:
This project is complete.