BELLE ISLE NEIGHBORHOOD - BID PACKAGE NO. 13B
PROJECT COMPLETED
 
 
Description
Funding
Implementation Schedule

 
 

DESCRIPTION
This project area encompasses the whole of Belle Island and includes both ROW Improvements and Park Enhancements. This corridor consists of high-density multi-family developments, with a small pocket of single-family and low density multi-family structures on the northeastern side of the island. Originally planned to be a part of the total Venetian Islands Project, the Belle Island was "split-out" as a separate package because it was deemed to be within a Priority drainage basin by the City’s PWD. On the other hand, the remainders of the Venetian Islands (DiLido, San Marino, Rivo Alto) were not. The Department of Environmental Management would not issue a permit for a complete project, if all islands did not receive stormwater improvements. However, not having been designated a Priority Basin, monies made available to the Venetian Islands through the bond issue were appropriately reallocated to fund shortfalls within other priority basins citywide. Hence, Bid Packages 13B and 13C were separated for permitting purposes.

The BP 13B Belle Isle and Belle Isle Park Project was completed as of June 2008.

For additional details, please click on the Photos Link to the left.

 

The Belle Isle and Belle Isle Park Neighborhood. Click photo to enlarge.
 
 

Return to top of page

FUNDING
The total construction and contingency budgets for the neighborhood improvements are as follows:
 

BID PACKAGE 13B BELLE ISLE FUNDING – Project Completed Oct 2008

General Obligation Bond

Water & Sewer Bonds

Stormwater Bonds

Stormwater Grant (FDEP)

Future Stormwater Bonds

$2,536,800

$1,906,376

$4,033,221

$400,000

$0

Total Proposed Funding

$8,876,397

 


Return to top of page

IMPLEMENTATION SCHEDULE

BID PACKAGE 13B BELLE ISLE - Implementation Schedule

Planning

Project Initiated at 50% Design Completion

Design & Permitting

41 months

November 2002 – March 2006

Bid / Award ( concurrent to design)

3 months

November 2005 – January 2006

Construction

28 months

May 2006 – August 2008

SYNOPSIS: This project is complete.